Heat Transfer CompoundsINSTALLATION PROCEDURES
Heat Transfer CompoundsCompound Preparation . . .1. Prior to installing compound, review the minimum applica-tion temperature limits listed below.Sur
INSTALLATION PROCEDUREST-3 and T-99 . . .Installation on Straight Run Piping 1. Install tube tracers in accordance with Illustrations A and B below.
Heat Transfer CompoundsIllustration C: Heat Transfer Compound InstallationInstallation on Valves, Flanges, Elbows and Pumps . . .1. Install tube tra
INSTALLATION PROCEDURES4T-80 and T-85 . . .Installation on Straight Run PipingTracers are to be run parallel and in direct contact with the process p
Heat Transfer Compounds5SnapTrace®. . .Installation on Straight Run PipingTracers are to be run parallel and in direct contact with the process pipe
INSTALLATION PROCEDURES6T-802 . . .Installation1. T-802 is installed just as T-80 and T-85.2. Mix the two-part compound.3. Install with a hand trow
Illustration H: Temperature Control DetailsIllustration I: Trapping and Condensate Handling DetailsSteam Temperature Control Using Self-Actuated Mecha